General (Active) Project Information
Phase 1C-5: Oyster Pond Sewer Extension (Contract 2022-CWMP-3A)
Project Name: Oyster Pond Sewer Extension, Phase 1C-5
Contract No.: 2022-CWMP-3A
CWSRF No.: 7079
Contractor: C.C. Construction Inc.
Engineer: GHD Inc.
Phase 1E-2: Stage Harbor Road Sewer Extension (Contract 2022-CWMP-3B)
Project Name: Stage Harbor Road Sewer Extension, Phase 1E-2
Contract No.: 2022-CWMP-3B
CWSRF No.: 7079
Contractor: Dig it Construction LLC
Engineer: GHD Inc.
Mill Pond Pumping Station Upgrade (Contract 2022-CWMP-4)
Project Name: Oyster Pond Sewer Extension, Mill Pond Pumping Station Upgrade
Contract No.: 2022-CWMP-4
CWSRF No.: 7072
Contractor: Robert B. Our Co.
Engineer: GHD Inc.
Phase 1D-2A: Route 137 - Morton Road (Contract 2019-CWMP-1)
Project Name: Phase 1D-2A: Route 137 - Morton Road Sewer Extension Project
Contract No.: 2019-CWMP-1
CWSRF No.: 4516
Contractor: C.C. Construction Inc.
Engineer: GHD Inc.
Queen Anne Pumping Station Upgrade (Contract 2021-CWMP-1)
Project Name: Queen Anne Pumping Station Upgrade
Contract No.: 2021-CWMP-1
CWSRF No.: 6768
Contractor: C.C. Construction Inc.
Engineer: GHD Inc.
Crowell Road Phase 2 and Chatham Fish Pier Project (Contract 2021-CWMP-2)
Project Name: Crowell Road Phase 2 and Chatham Fish Pier Infrastructure Project
Contract No.: 2021-CWMP-2
CWSRF No.: 6772
Contractor: N&M Excavating LLC
Engineer: GHD Inc.